Time Frame From Order To Shipment (Lead-Time)

Ordering process
Purchase order and color match
to be approved, if necessary

 

To be confirmed
Color, Gloss
Thickness, Panel size

 

Production lead-time
6 – 8 weeks

 

Transportation for delivery
Depending on the destination

Note 1:
The above time frame is pertinent to the standard ACM products: namely, ALPOLIC®/fr, ALPOLIC®/fr LT, ALPOLIC®, and AL-LEADER™.
Note 2:
TCM (Titanium Composite Material), SCM (Stainless Steel Composite Material) and ZCM (Zinc Composite Material) requires longer lead time than the above. Refer to “General Guidance
(Tabular Format)” of each product.