Ordering process
Purchase order and color match
to be approved, if necessary
Purchase order and color match
to be approved, if necessary
To be confirmed
Color, Gloss
Thickness, Panel size
Color, Gloss
Thickness, Panel size
Production lead-time
6 – 8 weeks
6 – 8 weeks
Transportation for delivery
Depending on the destination
Depending on the destination
Note 1:
The above time frame is pertinent to the standard ACM products: namely, ALPOLIC®/fr, ALPOLIC®/fr LT, ALPOLIC®, and AL-LEADER™.
Note 2:
TCM (Titanium Composite Material), SCM (Stainless Steel Composite Material) and ZCM (Zinc Composite Material) requires longer lead time than the above. Refer to “General Guidance
(Tabular Format)” of each product.